Moves per hour
Terminals measure a crane by moves per hour: 3600 seconds divided by the average cycle time. A twin lift spreader carries two 20 foot boxes in one move, doubling the boxes for the same cycle. Ship productivity multiplies that by the number of cranes working the vessel.
This is a simplified teaching model. Real averages are lower than the ideal number because of hatch covers, lashing, waiting for trucks and repositioning the crane along the ship.
Why the trolley path matters
The trolley travels farther to reach the outboard rows of a wide ship, which lengthens the cycle. That is one reason terminals invest in faster trolleys and longer outreach as ships get wider. The animation runs much faster than real time.