Why about 6 mm
A puddle of liquid on another liquid spreads until surface tension and gravity balance. For soda lime glass on tin that balance happens near 6 to 7 mm, so the float process makes that thickness almost for free. Every other thickness needs rollers or barriers working against it.
Output is ribbon width x thickness x speed x glass density. With a 3.3 m wide ribbon and a density of about 2.5 tonnes per cubic meter, the readout multiplies by 1,440 minutes per day.
What is simplified
The furnace check uses a rough teaching range of about 450 to 1,000 tonnes per day for one line. Real ribbons lose their thick edges when trimmed, and plants change speed and thickness together to keep the furnace pull steady. The drawn line is far shorter than a real one, which can run longer than a football field.