PUE (total power / IT power)–
Total facility power–
Overhead energy per year–
Drag to rotate, scroll or pinch to zoom

What PUE measures

PUE = total facility power / IT equipment power. Total power includes servers, cooling, lighting and losses in power conversion. A perfect facility would score exactly 1.0.

This teaching model computes cooling power as IT load divided by the cooling system's coefficient of performance (COP), adds a flat 8 percent of IT load for lighting and power conversion losses, and assumes containment cuts cooling power by 20 percent. Real savings depend on the building.

Try it: start at COP 3 without containment and note the PUE of about 1.41. Turn on containment, then raise COP to 7. The PUE drops toward 1.2 and hundreds of megawatt hours of overhead disappear each year.

Why it matters

Data centers use a measurable share of U.S. electricity, and AI computing is growing that share. Every bit of cooling overhead is paid for 8,760 hours a year, so hot and cold aisle layout, warmer supply temperatures and free cooling with outside air pay off quickly.

Where Avid uses this

Avid's founder began his career as an HVAC apprentice at 16, and the same airflow and heat removal principles behind building HVAC run every data center.

How to cite this model

Avid Solutions International. (2026, November 11). How a data center keeps servers cool [Interactive 3D model]. Avid Field Lab. https://avidsolutionsintl.com/explore/data-center-cooling